Container Terminal Kornik

Short description:
34.925 m² Gravel for gravel layer installed
33.000 m² Asphalt base layer
51.000 m² Asphalt binding layer
33.000 m² Asphalt surface course
36.000 m² hydraulically bound base layer
55.000 m² Earth stabilisation with chalk
87.000 m³ Earthworks, soil movement
1.900 m Drainage
840 m Rain water set up DN 200 – 600
100 m Waste water set up
4.900 m Cable duct laid

Buildingcosts:
Location: