Marine Engineering: Expansion of large ship waiting area

The joint venture between F+Z Baugesellschaft (TGF), Aug. Prien (KGF) and Taucher Knoth was awarded one of several alternative bids for the expansion of the Finkenwerder large ship waiting area. The berths are provided for the ships as waiting and emergency berths. In particular, the ships that can only sail on the Elbe in a given time window with large draughts depending on the tide are dependent on these berths. The complexity of the tender lay, among other things, in the fact that the complete draft planning, the bill of quantities as well as the statics had to be produced (Design & Build).

The full extension includes:   Production of 6 new mooring dolphins & 8 new mooring dolphins using the drilling method
Upgrading of the equipment of existing mooring and stiffened mooring dolphins
Measures for the absorption of traction forces from springlines for ships larger than 400m
Partial renovation corrosion protection at existing dolphins
Elimination of defects found during building inspection
Dismantling:
Dolphin berth A
Floodlight system berth A
Optional dismantling of the dolphin 121
Dolphins 1C

Employer: HPA Hamburg Port Authority AöR
Construction Period: Nov. 2018 -. End of October 2019
Specifications / Main Quantities: 6 new dolphins Ø2000 mm
8 new mooring dolphins Ø2300 mm
1 stiffened mooring dolphin
Demolition works
Technical processing Foundation Works Steel construction / corrosion protection Equipment
Explosive ordnance exploration

Buildingcosts: 15,5 € Mio.
Location: Hamburg Finkenwerder