Reconstruction Berth 9.3

By having issued a variant solution with an optimized foundation system the consortium of Bilfinger Marine & Offshore Systems GmbH and Kurt Fredrich Spezialtiefbau GmbH received the contract for the reconstruction of the Berth 9.3 in Cuxhaven. The execution took place between June 2016 and April 2017.

Specifications / Main Quantities:
368 pieces situ concrete pile, avg. 0,6x30m
micropiles GEWI 63.5
6.800 m³ of structural concrete in SB 2
Steel hydraulic structures
21.500m³ earthworks
4.000m² surface mounting
underground duct construction

Buildingcosts: 5,7 € Mio.
Location: Cuxhaven