Harbour Wyk Föhr Island
Upgrading of ferry pier 1 in the port of Wyk auf Föhr.
Technical data / main masses:
Dolphins 120 t
Sheet pile wall 1.200 t
Sand backfill 9.000 m³
Concrete 1.000 m³
Surface preparation 5.000 m²
Buildingcosts: 5,8 € Mio.
Location: Wyk Föhr Island