New Construction KV-Terminal Osnabrück

New construction of the entire combines transport plant including deconstruction, site preparation and area construction, as part of a consortium.

Services Depenbrock: 70.000 m² surface Removal and demolition of paved surfaces and buildings 50.000 m³ Profile regulating earthworks
2,2 km Construction rainwater sewer
0,5 km Construction waste water sewer
50.000 m² Preparation of asphalt pavement
160 m² Construction of a one-storey socail and gate building

Services cable civil engineering:
12.000 m Cable conduits
2 Track crossing
40 Precast concrete cable ducts

Buildingcosts: 12,7 Mio. €
Location: Osnabrück